Plant and Production Performance
Are plants and lines producing to plan?
Production vs plan: 91.3% against a ≥100% target (−8.7 pts); Plant 02 (78.4%) accounts for 7.6 of the 8.7 pts gap.
Root cause: Plant 02 made 95.2 of 121.5 kt planned. 78.2 h of unplanned downtime cost 14.8 kt (56% of its 26.2 kt shortfall), led by asset P02-03 on Line L2 (29 h of downtime). RM-1 cover is the secondary risk (4 days to breach).
Asset utilization: 91.9% against a ≥90% target (+1.9 pts); Plant 02 off target, offset by the other plants.
Root cause: Plant 02 ran 624.3 of 720 calendar hours (86.7%), losing 78.2 h to unplanned downtime, led by asset P02-03 on Line L2 (29 h of downtime).
OEE: 80.2% against a ≥80% target (+0.2 pts); Plant 02 off target, offset by the other plants.
Root cause: Plant 02 made 95.2 of 121.5 kt planned. 78.2 h of unplanned downtime cost 14.8 kt (56% of its 26.2 kt shortfall), led by asset P02-03 on Line L2 (29 h of downtime). RM-1 cover is the secondary risk (4 days to breach).
Capacity utilization: 79.8% against a ≥85% target (−5.2 pts); Plant 02 (70.0%) accounts for 5.1 of the 5.2 pts gap.
Root cause: Plant 02 made 95.2 of 121.5 kt planned. 78.2 h of unplanned downtime cost 14.8 kt (56% of its 26.2 kt shortfall), led by asset P02-03 on Line L2 (29 h of downtime). RM-1 cover is the secondary risk (4 days to breach).
Yield: 91.5% against a ≥92% target (−0.5 pts); Plant 03 (90.4%) moves it −0.7 pts, partly offset by Plant 02.
Root cause: Plant 03 yield is 90.4% (down 1.7 pts vs Aug), below the ≥92% target. The model records no process cause; this needs a plant process review.
Recovery %: 87.5% against a ≥88% target (−0.5 pts); Plant 03 (85.7%) moves it −1.1 pts, partly offset by Plant 01.
Root cause: Plant 03 recovered 31,527 t of 36,789 t contained in feed (85.7%, down 3.4 pts vs Aug). The model records no process cause; this needs a plant process review.
Plant 02 production · actual vs plan · kt per month (P07 forecast)
AnswersHow far below plan is Plant 02, and is it recovering?
P01–P06 certified plant data · P07 forecast = plan − 24.3 kt at risk (SIG-007).
Plant 02 P07 shortfall by line · kt (total 24.3 = SIG-007)
AnswersWhich production line loses the most output?