Synthetic data · thresholds placeholder · scenario time D0 06:40 (SYN)E-03

Asset Reliability and Recovery

Are assets reliable, and are we recovering lost output?

Scope Entity A1 (own entity) Period P07 MTD (SYN) Last refresh 06:25 (SYN) 6 of 6 cards certified Sources and lineage
MTBFREL-001
165h
Declining

MTBF: 165 h against a ≥200 h target (−35 h); Plant 02 (104 h) moves it −48.0 h, partly offset by Plant 03.

By plant · SepEffect on entity
Plant 01166 h▼ 189−11.3 h
Plant 02104 h▼ 47−48.0 h
Plant 03348 h▲ 170+24.6 h

Root cause: Plant 02: 6 breakdowns took 68.5 h to repair (MTTR 11.4 h vs ≤6.0 h), with only 27 of 33 preventive-maintenance jobs done; worst is asset P02-03 on Line L2 (29 h of downtime).

Plan≥ 200 h · var −35 h Trend▼ 37 vs P05 Forecast—
P01P06
Actual · P01–P06Plan
CERT P06
Refreshed 06:25Owner Maintenance (role)
Mean Time to RepairREL-002
8.2h
Declining

Mean Time to Repair: 8.2 h against a ≤6.0 h target (+2.2 h); Plant 02 (11.4 h) moves it +2.7 h, partly offset by Plant 01 and Plant 03.

By plant · SepEffect on entity
Plant 015.4 h▼ 1.6−0.2 h
Plant 0211.4 h▼ 0.3+2.7 h
Plant 034.4 h▼ 0.9−0.3 h

Root cause: Plant 02: 6 breakdowns took 68.5 h to repair (MTTR 11.4 h vs ≤6.0 h), with only 27 of 33 preventive-maintenance jobs done; worst is asset P02-03 on Line L2 (29 h of downtime).

Plan≤ 6.0 h · var +2.2 h Trend▲ 0.1 vs P05 Forecast—
P01P06
Actual · P01–P06Plan
CERT P06
Refreshed 06:25Owner Maintenance (role)
Unplanned downtimeREL-003
121h
Declining

Unplanned downtime: 121 h, up 25 vs Aug; Plant 02 contributes 65% (78 h).

By plant · SepShare
Plant 0130 h▲ 1125%
Plant 0278 h▲ 2565%
Plant 0312 h▼ 1110%

Root cause: Plant 02: 6 breakdowns took 68.5 h to repair (MTTR 11.4 h vs ≤6.0 h), with only 27 of 33 preventive-maintenance jobs done; worst is asset P02-03 on Line L2 (29 h of downtime).

Plan— · var — Trend▲ 25 vs P05 Forecast—
P01P06
Actual · P01–P06Plan
CERT P06
Refreshed 06:25Owner Maintenance (role)
Production loss from downtimeREL-004
21.7kt
Declining

Production loss from downtime: 21.7 kt, up 3.6 vs Aug; Plant 02 contributes 68% (14.8 kt).

By plant · SepShare
Plant 014.1 kt▲ 1.519%
Plant 0214.8 kt▲ 4.768%
Plant 032.8 kt▼ 2.613%

Root cause: Plant 02: 6 breakdowns took 68.5 h to repair (MTTR 11.4 h vs ≤6.0 h), with only 27 of 33 preventive-maintenance jobs done; worst is asset P02-03 on Line L2 (29 h of downtime).

Plan— · var — Trend▲ 3.6 vs P05 Forecast—
P01P06
Actual · P01–P06Plan
CERT P06
Refreshed 06:25Owner Maintenance (role)
Preventive-maintenance compliance [ASSUMED]REL-005
93.4%
Declining

Preventive-maintenance compliance: 93.4% against a ≥95% target (−1.6 pts); Plant 02 (81.8%) moves it −3.2 pts, partly offset by Plant 03.

By plant · SepEffect on entity
Plant 0193.5%▼ 3.4−0.5 pts
Plant 0281.8%▼ 13.1−3.2 pts
Plant 03100.0%flat+2.1 pts

Root cause: Plant 02 completed 27 of 33 scheduled preventive-maintenance jobs (81.8%). The skipped jobs line up with its 78.2 h of unplanned downtime.

Plan≥ 95.0% · var −1.6 pts Trend▼ 4.0 vs P05 Forecast—
P01P06
Actual · P01–P06Plan
CERT P06
Refreshed 06:25Owner Maintenance (role)
Critical plant-state alertsSIG-008
5alerts
Intervention required

Critical plant-state alerts: 5 alerts against a ≤0 alerts target (+5 alerts); Plant 02 contributes 80% (4 alerts).

By plant · SepShare
Plant 010 alerts▼ 20%
Plant 024 alerts▲ 180%
Plant 031 alert▼ 120%

Root cause: Plant 02 raised 4 of the 5 critical plant-state alerts, in line with its 78.2 h of unplanned downtime and MTTR of 11.4 h.

Plan≤ 0 alerts · var +5 alerts Trend▼ 2 vs P05 Forecast—
P01P06
Actual · P01–P06Plan
CERT P06
Refreshed 06:25Owner Maintenance (role)
Focus of this page

Plant 02 unplanned downtime by asset · h · P06 (CERT) · total 78.2 h = REL-003

AnswersWhich assets cause most unplanned downtime?

Asset P02-03 (SYN)
29 h
Asset P02-07
19 h
Asset P02-01
13 h
Asset P02-11
8 h
Other
9.2 h

Recovery plan vs actual · Plant 02

Milestone
Plan
Actual / forecast
Status
L2 re-sequencing published
D+1
On track
In progress
Planned maintenance P02-03 pulled into the low-RM-1 window
D+4
Proposed
Decision needed
Output back to plan
D+6 (with A + B)
Fcst D+6
Depends on DEC-SYN-0219

Named actions

Issue
Severity
Exposure
Named owner (role)
Due
Status
Escalation
Next action
Medium
Recovers 6 h downtime
Functional Leader (maintenance)
D+2
Proposed
L0
Approve schedule change